Year: 2015
Cost: MYR370,000
Description
The Lembaga Bandaran Johor Tenggara (LBJT) has appointed ISI to undertake the above study, the aim of which is to revitalise Bandar Tenggara. A 5-years action plan as the study final output is a development plan proposal with the supporting policies, strategies and programs to promote for the enhancement of its economic environment, the quality of the urban environment, quality of life and its physical growth.
The project cost of RM370,000.00 requires the preparation submission of four progress reports; inception report; interim report; draft final and Final Reports with the seven months study duration. The Final Report has been submitted on 5th November 2015 and accepted by LBJT. Thus the project is deemed complete.